Production scheduling problems of steelmaking-continuous casting process in dynamic production environment |
Zhong Zheng1,*,Jian-yu Long1,Xiao-qiang Gao2 |
1 College of Materials Science and Engineering, Chongqing University, Chongqing 400045, China 2 College of Economics and Business Administration, Chongqing University, Chongqing 400044, China |
|
|
Abstract A concept of production scenario for the steelmaking-continuous casting production process and the mathematical description of such concept were proposed. The production scenario was described with the variation of the equipment status and the production material properties based on the executing production schedule. Then, the dynamic characteristics of the production process could be described with the evolution process of production scenario. Through analyzing the influence of the dynamic production scenario on production scheduling, three key points about the scheduling problems were identified: the problem for integrating the schedules of different batches that is non-neglected when making a schedule, the problem for matching the material flow with the schedule that should be solved when implementing a schedule, and the problem for eliminating the deviations between the initial schedule and implemented schedule that should be solved when rescheduling in a disturbed environment. Finally, a set of experiments were conducted, and the results demonstrated that making the production schedule and solving the rescheduling problem for steelmaking-continuous casting process with addressing the above three problems improve the adaptability of the schedule in dynamic environment.
|
Received: 05 July 2016
Published: 06 June 2017
|
Fund:National Natural Science Foundation of China;National Natural Science Foundation of China;Key Projects of Chongqing Science and Technology Research Projects |
Corresponding Authors:
Zhong Zheng
E-mail: drzhengzh@sina.com
|
|
|
|
[1] |
Bang-fu Huang,,*,Nai-yuan Tian,Zhe Shi,,Zhi-wei Ma,. Steel ladle exchange models during steelmaking and continuous casting process[J]. Chinese Journal of Iron and Steel, 2017, 24(6): 617-624. |
[2] |
Jing-hui YANG,Jiu-ju CAI,Wen-qiang SUN,Jing-yu LIU. Optimization and Scheduling of Byproduct Gas System in Steel Plant[J]. Chinese Journal of Iron and Steel, 2015, 22(5): 408-413. |
[3] |
TAN Yuan-yuan,,HUANG Ying-lei,LIU Shi-xin,. Two-Stage Mathematical Programming Approach for Steelmaking Process Scheduling Under Variable Electricity Price[J]. Chinese Journal of Iron and Steel, 2013, 20(7): 1-8. |
[4] |
SUN Liang-liang,WANG Xiu-ying. Application of Mix Optimization Scheduling Approach for Steelmaking Continuous Casting Process Based on Actual Steelmaking Industry[J]. Chinese Journal of Iron and Steel, 2013, 20(10): 1-9. |
[5] |
LIU Wei,SUN Liang-liang. Steel-Making and Continuous/Ingot Casting Scheduling of Mixed Charging Plan Based on Batch Splitting Policy[J]. Chinese Journal of Iron and Steel, 2012, 19(2): 17-21. |
[6] |
YU Sheng-ping,PAN Quan-ke. A Rescheduling Method for Operation Time Delay Disturbance in Steelmaking and Continuous Casting Production Process[J]. Chinese Journal of Iron and Steel, 2012, 19(12): 33-41. |
|
|
|
|