Calculation model for the turnover number of steel ladles based on furnace-caster matching principle
CAI Jun1,WANG Hong-bing2,TIAN Nai-yuan1,XU An-jun1,HE Dong-feng1
(1. School of Metallurgical and Ecological Engineering, University of Science and Technology Beijing, Beijing 100083,China 2. School of Computer and Communication Engineering, University of Science and Technology Beijing, Beijing 100083, China)
Abstract:In order to optimize the production organization and dynamic-orderly operation in the steel-making plant,a scientifically reasonable calculation model for the number of turnover ladles was proposed. The turnover process of steel ladles was analyzed in Q steel-making plant. Based on furnace-caster matching principle,the relationship between the production rhythm of furnace-caster and the number of turnover ladles was analyzed with Gantt chart. A calculation model for the number of turnover ladles was proposed for some specific modes of furnace-caster matching. The research showed that the number of turnover ladles can be reduced by shortening flexible time of turnover ladles and overlap time between casting heats.
蔡 峻,汪红兵,田乃媛,徐安军,贺东风. 基于炉机匹配原则的周转钢包数量计算模型[J]. 钢铁, 2015, 50(7): 61-68.
CAI Jun,WANG Hong-bing,TIAN Nai-yuan,XU An-jun,HE Dong-feng. Calculation model for the turnover number of steel ladles based on furnace-caster matching principle. Iron and Steel, 2015, 50(7): 61-68.
YIN Rui yu.The evolution of the metallurgical processes function and the optimization of the steel structure. Acta Metall Sin,
[2]
YIN Rui yu.The evolution of the metallurgical processes function and the optimization of the steel structure. Acta Metall Sin,
[3].
[3].
[4]
TANG Lixin, WANG Gongshu.Decision support system for the batching problems of steelmaking and continuous-casting production[J].Omega, 2008, 36(6):976-980
[4]
TANG Lixin, WANG Gongshu.Decision support system for the batching problems of steelmaking and continuous-casting production[J].Omega, 2008, 36(6):976-980
[5]
Bellabdaoui A, Teghem J.A mixed-integer linear programming model for the continuous casting planning[J].International Journal of Production Economics, 2006, 104(2):260-270
[5]
Bellabdaoui A, Teghem J.A mixed-integer linear programming model for the continuous casting planning[J].International Journal of Production Economics, 2006, 104(2):260-270
[6]
Mohanty P P.An agent-oriented approach to resolve the production planning complexities for a modern steel manufacturing system[J].Int J Adv Manuf Technol, 2004, 24(3-4):199-205
[6]
Mohanty P P.An agent-oriented approach to resolve the production planning complexities for a modern steel manufacturing system[J].Int J Adv Manuf Technol, 2004, 24(3-4):199-205
[7]
ZHU Daofei, ZHENG Zhong, GAO Xiaoqiang.Intelligent optimization-based production planning and simulation analysis for steelmaking and continuous casting process[J]. Journal of Iron and Steel Research, International. 2010, 17(9): 19-24.
[7]
ZHU Daofei, ZHENG Zhong, GAO Xiaoqiang.Intelligent optimization-based production planning and simulation analysis for steelmaking and continuous casting process[J]. Journal of Iron and Steel Research, International. 2010, 17(9): 19-24.
[8]
Keshari K, Mukhopadhyay B, Das P C.Superheat control with efficient ladle management // 14th IAS Steelmaking Conference. San Nicolas, 2003: 395.
[8]
Keshari K, Mukhopadhyay B, Das P C.Superheat control with efficient ladle management // 14th IAS Steelmaking Conference. San Nicolas, 2003: 395.
LIU Qing, ZHAO Ping, WU Xiao dong, et al.Control strategy for ladle running[J].Journal of University of Science and Technology Beijing, 2005, 27(2):235-
[10]
LIU Qing, ZHAO Ping, WU Xiao dong, et al.Control strategy for ladle running[J].Journal of University of Science and Technology Beijing, 2005, 27(2):235-
LIU Qing, TIAN Naiyuan, HOU Wenyi, et al.Physical model of ladle cycling for converter plant[J].Journal of University of Science and Technology Beijing, 1999, 21(4):338-
[12]
LIU Qing, TIAN Naiyuan, HOU Wenyi, et al.Physical model of ladle cycling for converter plant[J].Journal of University of Science and Technology Beijing, 1999, 21(4):338-
[13]
王锋,田乃媛,贺东风,等.连铸机开浇前备包现象的讨论[J].钢铁, 2008, 43(3):41-
[13]
王锋,田乃媛,贺东风,等.连铸机开浇前备包现象的讨论[J].钢铁, 2008, 43(3):41-
[14]
WANG Feng, TIAN Naiyuan, HE Dongfeng, et al.Discussion on full ladle preparation for sequential casting[J].Iron and Steel, 2008, 43(3):41-
[14]
WANG Feng, TIAN Naiyuan, HE Dongfeng, et al.Discussion on full ladle preparation for sequential casting[J].Iron and Steel, 2008, 43(3):41-
CAI Jun, HE Dongfeng, WANG Hongbing, et al.Calculation model for the turnover number of steel ladle based on casting schedule[J].Chongqing: Chongqing University, 2013, 36(11):59-66
[16]
CAI Jun, HE Dongfeng, WANG Hongbing, et al.Calculation model for the turnover number of steel ladle based on casting schedule[J].Chongqing: Chongqing University, 2013, 36(11):59-66
HE Dongfeng, YU Gang, XU Anjun, et al.Productivity calculation using Gantt chart combination based on precise design[J]. Journal of University of Science and Technology Beijing. 2010, 32(12): 1618-1622.
[20]
HE Dongfeng, YU Gang, XU Anjun, et al.Productivity calculation using Gantt chart combination based on precise design[J]. Journal of University of Science and Technology Beijing. 2010, 32(12): 1618-1622.